Verity Rosa – progress of the construction works
Building A1 – construction shell structure; completion of roof insulation works; sanitary and electric installation works in progress
Building A2 – construction shell structure; completion of roof insulation works; sanitary and electric installation works in progress
Building A3 – construction shell structure; completion of roof insulation works, sanitary and electric installation works;
Building A4 – construction shell structure; completion of roof insulation works, sanitary and electric installation works;
Building B – construction shell structure; completion of roof insulation works, sanitary and electric installation works; installation of passenger’s lifts in progress; last stage of the elevation works; interior finishing works and installation of entrance doors in apartments in progress;
Building C – construction shell structure; completion of roof insulation works, sanitary and electric installation works; interior finishing works and installation of passenger’s lifts in progress;